CNG PUBLIC WORKS GARAGE UPGRADES<\/span>:<\/p>\n As a General Contractor, Design-Builder and Environmental Manager our list of services include: CNG PUBLIC WORKS GARAGE UPGRADES: Many cities are looking at the option of natural gas vehicles. With new federal funding available and an obvious cost savings over … Read More<\/a><\/p>\n","protected":false},"author":2,"featured_media":0,"parent":0,"menu_order":0,"comment_status":"closed","ping_status":"closed","template":"page-sidebar.php","meta":{"footnotes":""},"aioseo_notices":[],"jetpack_sharing_enabled":false,"jetpack_shortlink":"https:\/\/wp.me\/P6paBy-H","_links":{"self":[{"href":"https:\/\/dlkingnh.com\/wp-json\/wp\/v2\/pages\/43"}],"collection":[{"href":"https:\/\/dlkingnh.com\/wp-json\/wp\/v2\/pages"}],"about":[{"href":"https:\/\/dlkingnh.com\/wp-json\/wp\/v2\/types\/page"}],"author":[{"embeddable":true,"href":"https:\/\/dlkingnh.com\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/dlkingnh.com\/wp-json\/wp\/v2\/comments?post=43"}],"version-history":[{"count":2,"href":"https:\/\/dlkingnh.com\/wp-json\/wp\/v2\/pages\/43\/revisions"}],"predecessor-version":[{"id":1519,"href":"https:\/\/dlkingnh.com\/wp-json\/wp\/v2\/pages\/43\/revisions\/1519"}],"wp:attachment":[{"href":"https:\/\/dlkingnh.com\/wp-json\/wp\/v2\/media?parent=43"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}<\/a>Many cities are looking at the option of natural gas vehicles. With new federal funding available and an obvious cost savings over a diesel or gasoline powered fleet, it is a viable choice. However the garages where these busses or other vehicles are serviced, do need to be modified. Below are some details of a CNG PUBLIC WORKS GARAGE UPGRADE we did for the City of Nashua NH.<\/span><\/h3>\n
Scope of Work<\/span><\/h3>\n
Design-Build a NFPA and Bus-Garage Code Compliant separated CNG Repair Bay in the BPW Garage, 9 Stadium Dr. Nashua, NH; the upgrade of the garage bay (2500 SF) included common separation walls, doors and glazing meeting 2 HR Fire Rating; provide an intrinsically safe area in 18″ space below ceiling and a Gas Detection and Control System. Specifically:<\/span><\/h3>\n
*Separation Walls \u2013 2 Hr Fire Rated :<\/span><\/h3>\n
\u00a0\u00a0 >\u00a0\u00a0 6\u2019 high CMU wall with drywall above to ceiling<\/span><\/h3>\n
\u00a0\u00a0 > 14\u2019 W OVHD Common Door\/3 Hr Rated with Explosion proof motor and fire links<\/span><\/h3>\n
\u00a0\u00a0 >\u00a0 2 Hr Rated Mandoors<\/span><\/h3>\n
*Provide an Intrinsically safe area 18″ below Ceiling :<\/span><\/h3>\n
\u00a0\u00a0 >\u00a0 Relocate all electrical conduits, fixtures, outlets and lighting 24″ below ceiling<\/span><\/h3>\n
*Wall & Roof Exhaust Fans to Provide Five(5) Air Changes per Hour (ACH)<\/span><\/h3>\n
*Steam Unit Heater<\/span><\/h3>\n
*Replace Exterior OVHD Door Motors with Explosion Proof Motors<\/span><\/h3>\n
*Gas Monitoring and Control System<\/span><\/h3>\n
\u00a0\u00a0 >\u00a0 Gas Monitoring Control Panel with 911 Dialer, Audible & Visible alarms<\/span><\/h3>\n
\u00a0\u00a0 > \u00a0Control panel to activate OVHD Doors & Exhaust Fans<\/span><\/h3>\n
\u00a0\u00a0 > \u00a04 LPG Gas Sensors<\/span><\/h3>\n
Project was Federally Funded and Construction was Davis-Bacon Act Wage Rate compliant.<\/span><\/h3>\n
Work was 100% bonded.<\/span><\/h3>\n
\u00a0\u00a0\u00a0\u00a0 Also, this Design & Build Project was completed on-time, at Contract Cost (no change orders) and with quality workmanship. The quality, detail and responsiveness of the Design-Build Team and the outstanding cooperation of the BPW Garage Staff promoted the successful Project Delivery.<\/span><\/h3>\n
We would be pleased to provide services for your CNG Garage Upgrade.<\/span><\/h3>\n